Facilities Update
On Friday, August 28th, a site walk was held with our MOT staff and the selected contractor to review the site, planned improvements, and discuss timelines. At this point, we have a “semi-official” start date of Thursday, September 11th. Since they got a late start on the project, the contractor will work only on days students are not on campus, which means there will be no construction occurring during enrichment classes. While this schedule delays the project’s completion, student safety is our priority. Obviously, with the quad area completely torn up, access to the office and classrooms will be a little different, and we will share additional details once MOT and the contractor have determined what options provide the safest access to these buildings. While a little late, this is good news nevertheless, and the Gateway campus will be much improved once the project is completed.